來源:http://m.yelang007.com/ 發布時間:2018-04-27
1、材料及要求:
1, materials and requirements:
a.鋁合金板:鋁合金方板的規格600*600,厚度0.8毫米,孔徑¢3,穿孔率15%,鋁合金條板136寬搭接型鋁合金條板面層穿孔,板尺寸一致,顏色均勻,無裂紋、折斷、缺棱掉角。物品在運輸過程中一定要輕拿輕放,嚴禁受潮淋雨,得存放于干燥的環境、通風、避雨、下墊木板,要與墻壁保持一定的距離。
A. aluminum alloy plate: aluminum alloy square plate specification 600*600, thickness 0.8 millimeter, aperture 3, perforation rate 15%, aluminum alloy strip 136 wide lap type aluminum alloy strip surface layer perforation, plate size uniform, uniform color, no crack, break, edge off angle. In the course of transportation, it is necessary to take light and light in the course of transportation. It is strictly prohibited from wet rain. It must be stored in a dry environment, ventilation, shelter, and underlay wood. It is necessary to keep a certain distance from the wall.
b.鋁合金方板吊頂龍骨:T型輕鋼龍骨橫撐TB2*26,T型輕鋼次龍骨TB23*23,U型輕鋼主龍骨CB30*12、輕鋼次龍骨LB50*26、U型輕鋼主龍骨CB38*12。
B. aluminum alloy square plate ceiling keel: T type light steel keel cross brace TB2*26, T type light steel sub keel TB23*23, U type light steel main keel CB30*12, light steel sub keel LB50*26, U type light steel main keel CB38*12.
c.零配件:吊桿、角碼、絲桿和螺母、射釘、自攻螺釘、膨脹螺栓。
C. spare parts: suspender, corner code, screw and nut, nail, self tapping screw and expansion bolt.
2、主要機具:
2. Main machine tools:
a.電動工具:電鋸、無齒鋸、手電鋸、手電鉆、沖擊電錘、電動螺絲刀、電焊機。
A. electric tools: electric saw, toothless saws, hand saw, hand drill, impact hammer, electric screwdriver, electric welding machine.
b.手動工具:射釘槍、拉鉚槍、氣動直釘槍、氣動碼釘槍、手鋸、手刨子、鉗子、扳手、水準儀靠尺、鋼卷尺等。
B. manual tools: nail gun, rivet gun, pneumatic straight nail gun, pneumatic nail gun, hand saw, hand plane, pliers, spanner, level gauge, steel tape and so on.
3、工作條件
3. Working conditions
a.施工前應熟悉現場、圖紙和設計說明。
A. familiarity with site, drawings and design instructions before construction.
b.設計要求對房間的凈高、門洞標高和吊頂內的管道、設備及其支架的標高進行交接檢測。
The B. design requires that the height of the room, the height of the doorway and the elevation of the plumbing, the equipment and the support of the ceiling should be checked.
c.材料進場驗收記錄、檢驗報告、出廠合格證應齊全。
C. material acceptance check, inspection report and factory qualification certificate should be complete.
d.吊頂內的管道、設備安裝完成;罩面板安裝前上述設備應檢驗、試壓驗收合格。
The installation of pipe and equipment in the D. ceiling will be completed. The above equipment should be checked and tested before acceptance.
e.罩面板安裝前,墻、柱面裝飾基本完成,涂料只剩較后一面漆并驗收合格。
Before the E. panel was installed, the wall and cylinder decoration were basically completed. Only one last coat of paint was left.
f.行樣板工程,在樣板驗收合格后,再進行大面積吊頂。
F. carries out the prototype project first, then carries on the large area ceiling after the model acceptance is qualified.
關于鋁板生產廠家http://m.yelang007.com就先介紹到這里了,相信大家在實際的工作中會用到相關知識,如果您有這方面的需要,歡迎前來選購。
On the aluminum manufacturer http://m.yelang007.com first introduced here, I believe that you will use the relevant knowledge in the actual work, if you have the needs of this area, welcome to buy.